Project Progress

Construction update June 2014

The environmental impact assessment was approved on August 2013.
Construction has already started since September 2013

Summary construction progress as follows :

Construction update June 2014

The environmental impact assessment was approved on August 2013.
Construction has already started since September 2013

Summary construction progress as follows :

  Weight Percentage
Completed
Work has progressed
up to
1.Pilling Work     6%       100% Finish
2.Super Structure Work   23%       100% Footing Work
          100% Basement Work
          100% FL-1
          100% FL-2
            66% FL-3
3.Architectural Work   32%    
4.Interior Work   13%    
5.Systems Installation   25%