Construction update July 2014

The environmental impact assessment was approved on August 2013.
Construction has already started since September 2013

Summary construction progress as follows :

Construction update July 2014

The environmental impact assessment was approved on August 2013.
Construction has already started since September 2013

Summary construction progress as follows :

  Weight Percentage
Completed
Work has progressed
up to
1.Pilling Work     6%       100% Finish
2.Super Structure Work   23%       100% Footing Work, Basement Work
          100% FL-1 , 2 , 3 , 4 , 5
            60% FL-6
3.Architectural Work   32%         90% Masonry FL-2
             80% Masonry FL-3
            10% Masonry FL-4
4.Interior Work   13%    
5.Systems Installation   25%