Construction update August 2014

The environmental impact assessment was approved on August 2013.
Construction has already started since September 2013

Summary construction progress as follows :

Construction update August 2014

The environmental impact assessment was approved on August 2013.
Construction has already started since September 2013

Summary construction progress as follows :

  Weight Percentage
Completed
Work has progressed
up to
1.Pilling Work     6%       100.00 % Finish
2.Super Structure Work   23%         85.12 %  
3.Architectural Work   32%         14.53 %  
4.Interior Work   13%           2.00 %  
5.Systems Installation   25%