Construction update February 2014

The environmental impact assessment was approved on August 2013.
Construction has already started since September 2013

Summary construction progress as follows :

Construction update February 2014

The environmental impact assessment was approved on August 2013.
Construction has already started since September 2013

Summary construction progress as follows :

  Weight Percentage
Completed
Work has progressed
up to
1.Pilling Work 6% 100% Finish
2.Super Structure Work 23% 97% Footing Work
    10% Basement Work
3.Architectural Work 32%    
4.Interior Work 13%    
5.Systems Installation 25%