Construction update January 2015

The environmental impact assessment was approved on August 2013.
Construction has already started since September 2013

Summary construction progress as follows :

Construction update January 2015

The environmental impact assessment was approved on August 2013.
Construction has already started since September 2013

Summary construction progress as follows :

  Weight Percentage
Completed
Work has progressed
up to
 
1.Pilling Work     6%       100.00 % Finish  
2.Super Structure Work   23%       100.00 % Finish  
3.Architectural Work   32%         73.91 %    
4.Interior Work   13%           20.50 %    
5.Electrical and communication   12%         64.60 %    
6.Sanitary Systems     6%         100.00 %    
7.Ventilation Systems     7%         65.94 %