Construction update February 2015

The environmental impact assessment was approved on August 2013.
Construction has already started since September 2013

Summary construction progress as follows :

Construction update February 2015

The environmental impact assessment was approved on August 2013.
Construction has already started since September 2013

Summary construction progress as follows :

  Weight Percentage
Completed
Work has progressed
up to
 
1.Pilling Work     6%       100.00 % Finish  
2.Super Structure Work   23%       100.00 % Finish  
3.Architectural Work   32%         86.22 %    
4.Interior Work   13%           24.22 %    
5.Electrical and communication   12%         79.18 %    
6.Sanitary Systems     6%         100.00 % Finish  
7.Ventilation Systems     7%         98.13 %